Question discussion

Yesterday Shweta completed 300 units of work at the rate of 15 units per minute. Today she completed the same units of work but her speedwa…

109595Medium 1 reply 1,104 views
39
Yesterday Shweta completed 300 units of work at the rate of 15 units per minute. Today she completed the same units of work but her speedwas 40% faster than yesterday. What is the approximate difference in the time she took to complete the work yesterday and the time she took today ?
  • A16 min
  • B26 min
  • C46 min
  • D36 min
Answer not set

Discussion 1

0
CCommunity
Solution
Time taken by Shweta to complete 300 units of work at a speed of 15units/min = 300/15 = 20
New speed = 1.4*15 = 21 units/min
Time taken by Shweta to complete 300 units of work at a speed of 21units/min = 300/21 ~14
Time difference = 6 minutes