Solution
A alone can make 100 baskets in 6 days and B alone in 12 days
=> Rate of efficiency of A = $\frac{100}{6}$ baskets/day
Rate of efficiency of B = $\frac{100}{12} = \frac{50}{6}$ baskets/day
=> Baskets made by A and B together in 1 day = $\frac{100}{6} + \frac{50}{6}$
= $\frac{150}{6} = 25$ baskets/day
$\therefore$ Time taken by A and B together to make 100 baskets = $\frac{100}{25} = 4$ days