Eight men can dig a field in 14 days by working 6 hours a day. In how many days can 7 men dig the same field, by working 8 hours a day ?

127284Medium 1 reply 1,001 views
40
Eight men can dig a field in 14 days by working 6 hours a day.
In how many days can 7 men dig the same field, by working 8 hours a day ?
  • A12 days
  • B12.5 days
  • C14 days
  • D10 days
Answer not set

Discussion 1

0
CCommunity
$8 \times 14 \times 6 = 7 \times 8 \times x$

$x = 12$