12 men finished 1/4 part of whole work in 6 days. Find the number of additional men required to complete the job in next 6 days.

142708Medium 1 reply 709 views
0
12 men finished 1/4 part of whole work in 6 days. Find the number of additional men required to complete the job in next 6 days.
  • A36
  • B12
  • C18
  • D24
Answer not set

Discussion 1

0
CCommunity
12 men finished 1/4 part of whole work in 6 days,

⇒ 12 men finished whole work in 24 days,

⇒ Total work = 12 × 24 = 288 units,

Let x additional men are required,

Remaining work = 288 × 3/4 = 216 units

⇒ To finish 216 units work in next 6 days, men required = 216/6 = 36 men

∴ Additional men required are 24.