Question discussion

P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete th…

142987Medium 1 reply 2,949 views
55
P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?
  • A6 days
  • B5 days
  • C4 days
  • D3 days
Answer not set

Discussion 1

0
CCommunity
Time taken by Q to complete a job = 12 days

P is twice as efficient.

∴ Time taken by P to complete the job = 12/2 = 6 days

Work done by Q in 1 day = 1/12

Work done by P in 1 day = 1/6

Work done in 1 day = 1/12 + 1/6 = 3/12 = ¼

∴ Time taken by to complete the work together = 4 days.