Working together, A and B can complete a given task in 24 days. If the efficiencies of A and B are in the respective ratio of 3 ∶ 2, in how many days can B complete half of the task?
  • A18
  • B30
  • C15
  • D20
Answer not set

Discussion 1

0
CCommunity
Given,

(A + B) can complete a task in 24 days.

Let the efficiency of A and B be 3x and 2x.

Then in 24 days, total work done by (A + B) = 24 × (3x + 2x)

⇒ 24 × 5x = 120x

Half of task = 120x/2 = 60x

Than, B can complete half of the task = 60x/2x = 30 days