X can finish 25% of a work in day. Y can do 12.5% of the same work in a day. In how many days, will both of them finish the work together?

166295Medium 1 reply 573 views
0
X can finish 25% of a work in day. Y can do 12.5% of the same work in a day. In how many days, will both of them finish the work together?
  • A2.67 days
  • B2.33 days
  • C3.33 days
  • D3.67 days
Answer not set

Discussion 1

0
CCommunity
As per the given data,

No of days taken by X to finish the work = 100/25 = 4 days

⇒ Work done by X in one day = 1/4

No of days taken by Y to finish the work = 100/12.5 = 8 days

⇒ Work done by Y in one day = 1/8

∴ Work done by X and Y together to finish the work = 1/4 + 1/8 = 3/8

⇒ Number of days taken by X and Y together to finish the work = 8/3 = 2.67 days