A document containing detailed description of all the items of work (but their quantities are not mentioned) together with their current rates is called _________
  • ATender
  • BSchedule of rates
  • CAnalysis of rate
  • DAbstract estimate
Answer not set

Discussion 1

0
CCommunity
Schedule of rates:

A document containing detailed description of all the items of work (but their quantities are not mentioned) together with their current rates is called schedule of rates.

These usually include general conditions, general specifications, items of different works, data for transportation, materials and labor, method of rate analysis, plant rate analysis and basic unit rate analysis.