Question discussion

30 persons can finish a job in 20 days. After 6 days, how many persons should leave the job, so that work is completed in a total of 26 day…

179412Medium 1 reply 2,340 views
39
30 persons can finish a job in 20 days. After 6 days, how many persons should leave the job, so that work is completed in a total of 26 days?
  • A9
  • B12
  • C8
  • D7
Answer not set

Discussion 1

0
CCommunity
30 persons can finish a job in 20 days,

⇒ Total work = Days × men = 20 × 30 = 600 units

Work done in 6 days by 30 men = 6 × 30 = 180 units

⇒ Remaining work = 420 units

As the work is completed in a total of 26 days,

⇒ Remaining 420 units work to be completed in 20 days,

⇒ No of men = 420/20 = 21 men

∴ 9 men should leave.