Most accurate method of estimation is based on:

179806Medium 1 reply 780 views
23
Most accurate method of estimation is based on:
  • ABuilding cost index estimate.
  • BPlinth area estimate.
  • CDetailed estimate.
  • DCube rate estimate.
Answer not set

Discussion 1

0
CCommunity
Detailed estimate is the most accurate method and consist of working out the quantities of each of item of works and working the cost. The dimensions are taken directly from the drawings and quantities of each item are calculated. Finally abstracting and billing is done.

This is prepared in two stages.

1. Details of measurements and calculation of quantities

2. Abstract of Estimated Cost$

In the first stage, the quantity, availability, and transportation of materials parameters is being analyzed.$

In the second stage, the total abstract of the above analysis is shown.$