18 men or 25 boys can complete a work in 25 days. How many days will 36 men and 10 boys will take to complete the work?

183607Medium 1 reply 638 views
31
18 men or 25 boys can complete a work in 25 days. How many days will 36 men and 10 boys will take to complete the work?
  • A112/17
  • B125/12
  • C115/12
  • D125/17
Answer not set

Discussion 1

0
CCommunity
18 men 1 day work = 1/25

1 men 1 day work = 1/(18 × 25) = 1/450

36 men 1 day work = 36 × 1/450 = 2/25

Similarly,

25 boys 1 day work = 1/25

1 boy 1 day work = 1/(25 × 25) = 1/625

10 boys 1 day work = 10 × 1/625 = 2/125

Hence,

36 men and 10 boys 1 day work = 2/25 + 2/125 = 12/125

∴ 36 men and 10 boys will complete the work in 125/12 days