A is 25% more efficient then B. A works for ‘D’ days and completed 1/3 of work and left the work and remaining work is completed by B in ‘D…
184603Medium 1 reply 634 views
-1
A is 25% more efficient then B. A works for ‘D’ days and completed 1/3 of work and left the work and remaining work is completed by B in ‘D + 12’ day. In how many days A and B together can complete the work.