Question discussion

In which of the following the contractor undertakes the execution or construction of a specific work with all its contingencies, to complet…

190987Medium 1 reply 960 views
29
In which of the following the contractor undertakes the execution or construction of a specific work with all its contingencies, to complete it in all respect within a specified time for fixed amount?
  • AItem rate contract
  • BLump sum contract
  • CPercentage rate Contract
  • DSchedule contract
Answer not set

Discussion 1

0
CCommunity
Lump Sum Contract:

In this type of contract, the contractor undertakes the execution or construction of a specific work with all its contingencies, to complete it in all respect within a specified time for fixed amount.

The contract agreement in lump sum contract includes:

- Detailed specification of all the items of works pertaining to the whole work

- Plan and detailed drawing

- Deposit of 10% security money

- Penalty

- Progress and other condition of the contract

- On completion of the work whole work is compared and checked with plans and drawing