A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
  • A20
  • B30
  • C18
  • D24
Answer not set

Discussion 1

0
CCommunity
Suppose unit work = 300 units (LCM of 50, 75 & 20)

∴ Work done by A in one day = 300/50 = 6

Work done by B in one day = 300/75 = 4

Work done by C in one day = 300/20 = 15

∴ Work done by (A + B + C) in 4 days = 4 × (6 + 4 + 15) = 100

C quits after 4 days.

∴ Remaining work after 4 days = 300 – 100 = 200 units

∴ Time taken by A and B together to complete 200 units = 200/(6 + 4) = 20 days