Smita can finish a work in 12 days and Sam can finish the same work in 9 days.After working together for 4 days they both leave the job. Wh…
195356Medium 1 reply 1,437 views
42
Smita can finish a work in 12 days and Sam can finish the same work in 9 days.After working together for 4 days they both leave the job. What is the fraction of unfinished work?