Question discussion

A takes 12 days less than the time taken by B to finish a piece of work. If both A and B can do it in 8 days, then the time taken by B alon…

198072Medium 1 reply 1,095 views
0
A takes 12 days less than the time taken by B to finish a piece of work. If both A and B can do it in 8 days, then the time taken by B alone to finish the work is
  • A24 days
  • B28 days
  • C20 days
  • D16 days
Answer not set

Discussion 1

0
CCommunity
Given, A takes 12 days less than the time taken by B to finish a piece of work.

Let the number of days in which B finishes the work be ‘a’ days

Number of days in which A finishes the work = a – 12 days

Now, both A and B can do it in 8 days.

$(\Rightarrow \frac{1}{a} + \frac{1}{{a - 12}} = \frac{1}{8})$

⇒ (a + a -12) × 8 = a2 – 12a

⇒ a2 – 28a + 96 = 0

⇒ a2 – 24a - 4a + 96 = 0

⇒ a(a – 24) – 4(a – 24) = 0

⇒ (a – 4)(a – 24) = 0

⇒ a can’t be 4 thus a = 24 days