Question discussion

A alone can do a work in 20 days. B is 25% more efficient than A. A and B started working and worked for 4 days. If C alone completed the r…

199787Medium 1 reply 3,721 views
37
A alone can do a work in 20 days. B is 25% more efficient than A. A and B started working and worked for 4 days. If C alone completed the remaining job in 22 days. How many days C alone takes to complete the entire job?
  • A24 days
  • B36 days
  • C12 days
  • D20 days
Answer not set

Discussion 1

0
CCommunity
A alone can do work in 20 days.

B is 25% more efficient than A.

⇒ B can do a work in 16 days.

Let the total unit of work ( LCM of 20 and 16) = 80 units

⇒ A’s one day work = 4

⇒ B’s one day work = 5

As A and B left after working for 4 days.

⇒ Work done by A and B in 4 days = 36 work

⇒ Work left = 44 units is done by C in 22 days.

⇒ C’s one day work = 2 units

∴ 80 units of work can be completed by C alone in 80/2 = 40 days