Manju takes 16 days to complete a work. If she works with her friend Jenny they complete it in 12 days. How many days will it take for Jenn…

205962Medium 1 reply 573 views
0
Manju takes 16 days to complete a work. If she works with her friend Jenny they complete it in 12 days. How many days will it take for Jenny to complete the work alone?
  • A48
  • B32
  • C36
  • D24
Answer not set

Discussion 1

0
CCommunity
Time taken by Manju alone to complete the work = 16 days

Time taken by Manju and Jenny to complete the work when they work together = 12 days

Total work = L. C. M of 16 and 12 = 48 units

One day work of Manju = 48 ÷ 16 = 3 units

One day work of Manju and Jenny = 48 ÷ 12 = 4 units

∴ one day work of Jenny = 1 unit

Time taken by Jenny alone to complete the work = 48 ÷ 1 = 48 days