The efficiency of work of P and Q are in the ratio 5 : 7. What will be the ratio of number of days taken by them to finish the work?

212272Medium 1 reply 1,693 views
29
The efficiency of work of P and Q are in the ratio 5 : 7. What will be the ratio of number of days taken by them to finish the work?
  • A7 : 5
  • B3 : 4
  • C4 : 3
  • D5 : 7
Answer not set

Discussion 1

0
CCommunity
We know that efficiency $(\propto {\rm{\;}}\frac{1}{{no\;of\;working\;days}})$

Given that efficiency of work P and Q are in the ratio of 5 : 7

∴ Ratio of number of days taken by them to finish the work = 7 : 5