Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then…

219256Medium 1 reply 657 views
15
Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then in how many days the book will be completed?
  • A28
  • B25
  • C24
  • D30
Answer not set

Discussion 1

0
CCommunity
Let Puneet complete the book = a days

So, Manish complete the book = 4a days

Difference of days = 4a – a = 3a = 90 days

⇒ a = 30 days

Time taken by Puneet = a = 30 days

Time taken by Manish = 4a = 120 days

Let Total work = Lcm of 30 and 120 = 120 units

Efficiency of Puneet = 120/30 = 4 units/day

Efficiency of Manish = 120/120 = 1 unit/day

Total Efficiency of Puneet and Manish = 4 + 1 = 5 units/day

∴ Total time taken to complete the book = 120/5 = 24 days