P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?

241682Medium 1 reply 1,091 views
35
P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?
  • A6 days
  • B3 days
  • C12 days
  • D9 days
Answer not set

Discussion 1

0
CCommunity
⇒ One - day work of P = 1/25

⇒ One - day work of Q = 1/50

⇒ One - day work of both P and Q together = 1/25 + 1/50 = 3/50

⇒ Total time taken by them = 50/3 days

⇒ Time taken for 18% work = (18/100) × (50/3) = 3 days