A company calculates the prices of jobs by adding overheads to the prime cost and adding 30% to total costs as a profit margin. Job number Y256 was sold for Rs1690 and incurred overheads of Rs 694. What was the prime cost of the job?
  • ARs 489
  • BRs 606
  • CRs 996
  • DRs 1300
Correct answer: B

Discussion 1

0
CCommunity
Rs 606