While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objectiv…

316048Medium 1 reply 1,656 views
25
While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to?
  • AMinimize total cost of assignment
  • BReduce the cost of assignment to zero
  • CReduce the cost of that particular assignment to zero
  • DAll of the above
Correct answer: A

Discussion 1

0
CCommunity
Minimize total cost of assignment

While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to minimize total cost of assignment. The objective of assignment problem is to assign a number of jobs to an equal number of machines so as to minimize the total assignment cost or to minimize the total consumed time for execution of all the jobs. In the multi-objective assignment problem, the objectives alone are considered as fuzzy.