A can do a piece of work in 21 days and B in 28 days. Together they started the work and B left after 4 days. In how many days can A alone…
322424Medium 1 reply 514 views
21
A can do a piece of work in 21 days and B in 28 days. Together they started the work and B left after 4 days. In how many days can A alone do the remaining work?