Question discussion

A, B and C can do a work in 7 , 14 and 21 days respectively. They completed the work and got Rs.242. What is the share of C?

324605Medium 1 reply 866 views
1
A, B and C can do a work in 7 , 14 and 21 days respectively. They completed the work and got Rs.242. What is the share of C?
  • ARs.55
  • BRs.44
  • CRs.66
  • DRs.77
Correct answer: B

Discussion 1

0
CCommunity
Rs.44

The ratio of their working rates = 1/7 : 1/14 : 1/21 = 6 : 3 : 2.
Since, they work together, the share of C
= 2/11 * 242 = Rs.44