A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many day…

325047Medium 1 reply 4,396 views
38
A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?
  • A10 days
  • B20 days
  • C5 days
  • D4 days
Correct answer: B

Discussion 1

0
CCommunity
20 days

C = 1/2 - 1/4 - 1/5 = 1/20 => 20 days