45 men working 8 hours per day dig 30 m deep. How many extra men should be put to dig to a depth of 50 m working 6 hours per day?

327229Medium 1 reply 1,403 views
1
45 men working 8 hours per day dig 30 m deep. How many extra men should be put to dig to a depth of 50 m working 6 hours per day?
  • A25
  • B30
  • C45
  • D55
Correct answer: D

Discussion 1

0
CCommunity
55

(45 * 8)/30 = (x * 6)/50 => x =100

100 – 45 = 55