A, B and C can do a piece of work in 7 days, 14 days and 28 days respectively. How long will they taken, if all the three work together?

328066Medium 1 reply 502 views
-1
A, B and C can do a piece of work in 7 days, 14 days and 28 days respectively. How long will they taken, if all the three work together?
  • A3 days
  • B4 days
  • C5 days
  • D6 days
Correct answer: B

Discussion 1

0
CCommunity
4 days

1/7 + 1/14 + 1/28 = 7/28 = 1/4 => 4 days