After working for 6 days, Ashok finds that only 1/3 rd of the work has been done. He employs Ravi who is 60% as efficient as Ashok. How many days more would Ravi take to complete the work?
  • A19 days
  • B10 days
  • C20 days
  • D12 days
Correct answer: C

Discussion 1

0
CCommunity
20 days

1/3 ---- 6

1 -------? A = 18

R = 1/18 * 60/100 = 1/30

1 ----- 1/30

2/3 ----? => 20 days