A contractor decided to build a bridge in 35 days. He employed 60 men in the beginning and 40 more after 17 days and completed the work on…

328790Medium 1 reply 1,996 views
34
A contractor decided to build a bridge in 35 days. He employed 60 men in the beginning and 40 more after 17 days and completed the work on time. If he had not employed the additional men, how many day
  • A10 days
  • B11 days
  • C12 days
  • D13 days
Correct answer: D

Discussion 1

0
CCommunity
13 days

Let 60 men complete the work in x days
60 men