If 40 men working 9 hours a day can finish a work in 21 days, in how many days will 27 men working 10 hours a day do the same work?

329677Medium 1 reply 566 views
0
If 40 men working 9 hours a day can finish a work in 21 days, in how many days will 27 men working 10 hours a day do the same work?
  • A1 hr
  • B2 hrs
  • C3 hrs
  • D4 hrs
Correct answer: D

Discussion 1

0
CCommunity
4 hrs

That is, 1 work done = 40 × 9 × 21

Then, 40 × 9 × 21 = 27 × 10 × ? days

Therefore, ? days = 40× 9 × 21 /27 × 10 = 28 days.

= 4 hours.