A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
  • A50 days
  • B60 days
  • C70 days
  • D80 days
Correct answer: B

Discussion 1

0
CCommunity
60 days

A + B’s 1 day’s work = 1/30

i.e. A + B = 1/30 --------- (i)

16 A + 44 B = 1 ------ (ii) ( i.e. 1 = the whole work done)

Multiplying (i) by 16 and subtracting it from (ii), we get

i.e. 16 A + 44 B = 1

16 A + 16B = 8/15

28 B =7/15

B = 1/60 i.e. B’s 1 day’s work = 1/60

Therefore, B alone can finish the work in 60 days.