A work which could be finished in 9 days was finished 3 days earlier after 10 more men joined. The number of men employed was?

349578Medium 1 reply 7,827 views
-3
A work which could be finished in 9 days was finished 3 days earlier after 10 more men joined. The number of men employed was?
  • A18
  • B20
  • C22
  • D24
Correct answer: B

Discussion 1

0
CCommunity
20

x ------- 9

(x + 10) ---- 6

x * 9 = (x + 10)6

x = 20