0
A contractor undertakes to complete the construction of a tunnel 720 meters long in 240 days and employs 60 men for the purpose. After 120 days, he finds that only 240 meters of the tunnel is complete
- A70 men
- B60 men
- C55 men
- D80 men
Correct answer: B