Question discussion

A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The li…

354975Medium 1 reply 1,166 views
15
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?
  • A1.0 hour per unit
  • B1.2 hours per unit
  • C1.4 hours per unit
  • D1.6 hours per unit
Correct answer: A

Discussion 1

0
CCommunity
1.0 hour per unit