Question discussion

Either 8 men or 17 women can paint a house in 33 days. The number of days required to paint three such houses by 12 and 24 women working at…

49470Medium 1 reply 635 views
40
Either 8 men or 17 women can paint a house in 33 days. The number of days required to paint three such houses by 12 and 24 women working at the same rate is :
  • A44 days
  • B43 days
  • C34 days
  • D66 days
Answer not set

Discussion 1

0
CCommunity
Total work = $ \Large 17 \times 33 \times 3 $

Let 1 woman works 1 unit/day then 17 women will do 17 units / day) .

$ \Large 12 men + 24 women $

$ \Large \frac{51}{2} women +\frac{24}{1}women=\frac{99}{2} $ women

will do $ \Large 17 \times 33 $ work in

=$ \Large \frac{17 \times 33}{\frac{99}{2}} \times 3 $=34 days