2 women and 10 children together take 8 days to complete a piece of work How many days will 10 children alone take to complete the piece of…

99918Medium 1 reply 2,404 views
36
2 women and 10 children together take 8 days to complete a piece of work How many days will 10 children alone take to complete the piece of work if 8 women alone can complete the piece of work in 6 days ?
  • A15
  • B12
  • C10
  • D24
Answer not set

Discussion 1

0
CCommunity
Solution
Let the speed of women be x and that of children be y. Let the piece of work be W.

2x + 10y = W/8

8x = W/6

x = W/48

Hence, we get y= W/120

Speed of 1 child = W/120

Speed of 10 children = W/12

Now time needed for them to complete = W/(W/12) =12days

Therefore, the correct option is B.