A system has four processes and three resource types. The allocation, maximum demand and the currently available resources are given below. Which of the following is a safe sequence?
Process Allocation Maximum
P0 2 2 0 5 2 0
P1 1 0 0 3 0 1
P2 1 2 1 2 4 1
P3 1 1 1 4 1 4
Available = (2, 1, 2)- AP3, P2, P1, P0
- BP0, P1, P2, P3
- CP2, P1, P0, P3
- DP1, P0, P2, P3
Correct answer: D