Given, work done by (x + 4) men in (x + 5) days is equal to the work done by (x – 5) men in (x + 20) days.

∴ Total work = (x + 4)(x + 5) = (x – 5)(x + 20)

⇒ x2 + 9x + 20 = x2 + 15x -100

⇒ 6x = 120

⇒ x = 20