According to the Basic COCOMO model, the effort of an organic-mode project is E = 2.4 x (KLOC)^1.05 person-months. For a project of 10 KLOC, the effort is approximately

  • A57.1 person-months
  • B24.0 person-months
  • C39.5 person-months
  • D26.9 person-months
Correct answer: D

Explanation

E = 2.4 x 10^1.05 = 2.4 x 11.22 = about 26.9 person-months.