According to the Basic COCOMO model, the effort of an organic-mode project is E = 2.4 x (KLOC)^1.05 person-months. For a project of 10 KLOC, the effort is approximately
- A57.1 person-months
- B24.0 person-months
- C39.5 person-months
- D26.9 person-months
Correct answer: D