In a project network, activity A (3 days) must finish before activities B (2 days) and C (4 days) can start, and activity D (1 day) can start only after both B and C are finished. What is the minimum duration of the project?

  • A6 days
  • B8 days
  • C7 days
  • D10 days
Correct answer: B

Explanation

The critical path is A → C → D = 3 + 4 + 1 = 8 days, since B (2 days) runs in parallel with the longer activity C.