0
In a project network, activity A (3 days) must finish before activities B (2 days) and C (4 days) can start, and activity D (1 day) can start only after both B and C are finished. What is the minimum duration of the project?
- A6 days
- B8 days
- C7 days
- D10 days
Correct answer: B