A is twice as efficient as B. Together they can finish a piece of work in 18 days. In how many days can A alone finish the work?

2448Medium DSSSB TGT Computer Science 0 replies

A is twice as efficient as B. Together they can finish a piece of work in 18 days. In how many days can A alone finish the work?

  • A30
  • B36
  • C54
  • D27
Correct answer: D

Explanation

With efficiencies 2 and 1 the total work is 18 × 3 = 54 units, and A alone does 2 units a day, so he takes 54 / 2 = 27 days.