0
Two project risks are identified: R1 has a probability of 0.3 and a loss of ₹4,00,000 if it occurs, and R2 has a probability of 0.1 and a loss of ₹15,00,000 if it occurs. The total risk exposure is
- A₹19,00,000
- B₹1,20,000
- C₹1,50,000
- D₹2,70,000
Correct answer: D