Two project risks are identified: R1 has a probability of 0.3 and a loss of ₹4,00,000 if it occurs, and R2 has a probability of 0.1 and a loss of ₹15,00,000 if it occurs. The total risk exposure is

  • A₹19,00,000
  • B₹1,20,000
  • C₹1,50,000
  • D₹2,70,000
Correct answer: D

Explanation

Risk exposure = probability × loss, so it is 0.3 × 4,00,000 + 0.1 × 15,00,000 = 1,20,000 + 1,50,000 = ₹2,70,000.