Question discussion

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on fir…

31880Medium 2 replies 2,086 views
33
A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
  • A17
  • B19
  • C19.5
  • D21
Answer not set
0
CCommunity
i think option 2 is correct
0
CCommunity
B -> x days

A -> (x - 8) days

Total work = x(x - 8)

Now x = 1.5(x - 8)

since the efficiency of a is 1.5 times that of B .

On solving, we get, x = 24

therefore total work = x(x - 8) = 384

which can be completed by A with an efficiency of 24 and B with an efficiency of 16 alternately, starting with A in 19 days.