A completes a work in 12 days and B complete the same work in 24 days. If both of them work together, then the number of days required to c…

322912Medium 2 replies 656 views
1
A completes a work in 12 days and B complete the same work in 24 days. If both of them work together, then the number of days required to complete the work will be
  • A8 days
  • B9 days
  • C10 days
  • D11 days
Correct answer: A
0
CCommunity
8 days

If A can complete a work in x days and B can complete the same work in y days, then, both

of them together can complete the work in x y/ x+ y days

Therefore, here, the required number of days = 12 × 24/ 36 = 8 days.
0
CCommunity
A's 1 day's work = 1 / 12

B's 1 day's work = 1/ 24

(A + B)'s 1 day's work = 112+124

=2+124=<span id="MathJax-Span-24" class="mn" style="box-sizing: border-box; transition: none 0s ease 0s; display: inline; position: static; border: 0px; padding: 0px; margin: 0px; vertical-align: 0px; line-height: normal; font-size: 18.324px; font-family: MathJax_Mai