P is 20 percent more efficient than Q. P alone can do a work in 2 days less than Q alone. In how many days can they do the work together?
- A54/11
- B53/9
- C60/11
- D40/9
Correct answer: C
P is 20 percent more efficient than Q. P alone can do a work in 2 days less than Q alone. In how many days can they do the work together?