P is 20 percent more efficient than Q. P alone can do a work in 2 days less than Q alone. In how many days can they do the work together?

359755Medium DSSSB TGT Computer Science 0 replies 0 views
0

P is 20 percent more efficient than Q. P alone can do a work in 2 days less than Q alone. In how many days can they do the work together?

  • A54/11
  • B53/9
  • C60/11
  • D40/9
Correct answer: C

Explanation

P : Q efficiency = 6 : 5, so the days taken are in the ratio 5 : 6. The difference of 1 part = 2 days, so P takes 10 days and Q takes 12 days. Together: 1/(1/10 + 1/12) = 60/11 days.