Question discussion

The SRS document produced at the end of requirement analysis and specification is known as ______.

360054Medium DSSSB TGT Computer Science 0 replies 0 views
0
The SRS document produced at the end of requirement analysis and specification is known as ______.
  • Awhite-box specification
  • Bblack-box specification
  • Cdesign plan
  • Darchitectural design
Correct answer: B

Explanation

The SRS produced at the end of the requirements phase is a black-box specification, since it describes external behaviour only.

Discussion 0

Nobody has replied yet. Start the discussion!