A can do a certain work in 14 days. B is 331⁄3% less efficient than A. Both started to work together, but A left the work 2 days before the completion of the work and B continued to work till the work was over. In how many days was the whole work completed?
- A93⁄5
- B81⁄4
- C81⁄2
- D102⁄5
Correct answer: A