Which of the following is NOT true about the Waterfall model?

3707Medium DSSSB TGT Computer Science 0 replies 2 views
0

Which of the following is NOT true about the Waterfall model?

  • ALong duration
  • BHigh cost
  • CHigh-risk involvement
  • DLow cost
Correct answer: B

Explanation

The waterfall model has a long duration, high cost and high risk (as per the official key). Option 2 ‘High cost’ is marked as not true.