Assume that the following jobs are to be executed on a single processor system. All jobs have arrived at 0 msec.
If scheduling is round robin with time slice 1 msec, then what is the completion time for job ‘a’?
If scheduling is round robin with time slice 1 msec, then what is the completion time for job ‘a’?

- A11
- B10
- C4
- D7
Correct answer: B